Stainless steel pump skid with flanged headers and vertical multistage pumps
Brine concentration & zero liquid discharge

Engineering for the most concentrated water on site.

Independent process engineering for high-salinity brines: membrane and thermal concentration trains, MLD and ZLD scoping, metallurgy, and the economics of replacing off-site hauling. Vendor-neutral, with the math in the open.

Salinity operating envelope

Every technology has a TDS ceiling and an energy price.

Feed salinity decides where membranes stop and evaporation begins. Specific energy consumption (SEC) climbs roughly an order of magnitude at each handoff, which is why train order matters more than any single unit.

5,000–70,000Brackish / Seawater ROSEC 2.5–5.0 kWh/m³
→ 120,000–130,000High-Pressure RO (HPRO)SEC 5–10 kWh/m³
→ 100,000–140,000OARO / CFROSEC 6–20 kWh/m³
→ 200,000–250,000+MVR Brine ConcentratorSEC 40–80+ kWh/m³
Dry salt cakeCrystallizer / ATFDSEC 60–110+ kWh/m³

TDS in mg/L. SEC per m³ of water removed at that stage. Basis: process train overview and methodology.

Engineering tools

Two calculators engineers can put in a capital request.

Both run in the browser, share by link and print to a one-page sheet. Inputs and formulas are published on the methodology page.

MLD/ZLD Mass Balance & Lifecycle Cost Modeler

Enter flow, TDS and chemistry. Get the recommended stage sequence, water recovered and reject TDS at each stage, kWh and power draw, wetted metallurgy and a Class 5 CAPEX/OPEX range.

  • GPM or m³/day, 5,000–200,000 mg/L feed
  • Hybrid membrane-thermal vs. direct thermal energy comparison
  • Levelized operating cost in $/m³ and $/gal
Open the modeler

Brine Hauling vs. On-Site Evaporator ROI

For plants trucking brine today. Compare escalating hauling spend with an atmospheric, vacuum heat-pump or MVR evaporator and see payback, tanker loads removed and 5-year cumulative cash flow.

  • Non-hazardous, high-TDS and RCRA hazardous presets
  • Auto-estimated or manual CAPEX
  • Year-by-year cash flow table for the CFO
Open the ROI calculator
Process trains

Choose the train before you choose the vendor.

OARO vs. MVR brine concentrators

Osmotically assisted RO reaches 100,000–140,000 mg/L at 6–20 kWh/m³; MVR reaches saturation at 40–80+ kWh/m³. Putting OARO ahead of MVR typically cuts total ZLD operating cost by 25–40%.

Compare the two

MLD vs. ZLD

The final 5–10% of water drives 40–60% of plant energy and capital. Where a brine line, deep well or small pond exists, minimum liquid discharge is often the better engineering answer.

See the trade-offs

BMED brine valorization

Bipolar membrane electrodialysis splits softened NaCl concentrate into NaOH and HCl at 1.25–2.2 kWh/kg NaOH for dilute product, offsetting purchased caustic and acid.

Read the guide
Disposal cost reality

What the brine costs you to get rid of today.

The disposal route sets the budget for everything upstream. When hauling or ponds pass roughly $10/m³, on-site concentration usually starts paying back.

Ranges and sources: full disposal tariff dataset (CSV).
Disposal routeTypical costMain constraint
Surface water / ocean outfall$0.05–$0.50 /m³NPDES permit, receiving-water limits
Dedicated brine line (e.g. SAWPA)~$0.30 /m³ + treatment & BOD/TSS chargesCapacity units, few basins have one
UIC Class I/II deep well$0.50–$3.00 /m³ piped; $2–$10+ /m³ trucked1–3 year permit, seismic and MIT scrutiny
Tanker hauling$0.05–$10.00+ /gal by waste classEscalating rates, RCRA generator liability
On-site MLD / ZLD$10–$45+ /m³ operatingEnergy 50–70% of OPEX, salt cake disposal
Open the full tariff and utility dataset
How a project runs

From lab report to basis of design in four steps.

  1. Ion chromatography & charge balance audit

    Validate the lab report: cation/anion balance within ±5%, saturation indices for CaSO₄, CaCO₃, BaSO₄ and silica at each concentration factor.

  2. Bench-scale softening & treatability

    Lime/soda or NF softening jars, antiscalant screening and boiling-point-rise checks before any skid is sized.

  3. Skid pilot program

    Weeks of real feed through membrane and evaporator pilots to confirm flux, scaling margin, distillate quality and salt cake behavior.

  4. Basis of design & vendor bid review

    A single mass balance every bidder prices against, then a line-by-line review of guarantees, metallurgy and exclusions.

Send us the stream before you buy the skid.

Share flow, TDS and a lab ion report. We return a preliminary mass balance, a train recommendation and the questions a vendor bid has to answer.